These photos were taken the final week of Decemeber.
Mid-Dec Report, posted Dec. 12
Precast installation is complete
Roof is complete in area A (classroom) and the area is being heated
Roof decking is complete in area C (shop) and in Kitchen
Bar joists are complete in area B (gym) and roof decking will be completed soon
Dec. 3 Report
n
The left photo is looking from the front door to the north into our commons/cafetorium. The 2nd picture is looking into the gym from the south looking north. The opening should be enclosed by late next week.
Mid-November Report
n
The photo on the left shows the curved wall of the cafatorium.
Mid-October Report: Precast walls starting to go up - rooms taking shape
Site photos - taken Sept. 22
Interior and exterior brickwork - August 29
Exterior block completed on south, east, and north walls on the east side of the building. Interior footings are being poured and interior block is being installed. The plumbing rough-in is underway. Electrical crew is on site to begin their rough-in work. It is amazing what can happen in just a few weeks
Forms and cement work has started on the eastside of the building - August 1
Building Site - Geopier Drilling, July 14
These photos were taken at the Hills-Beaver Creek High School Building Site in mid-July.
Building Site - Geopier Drilling, July 2
High School Building Site - Ground Breaking June 11